Net Metering in Pakistan: Complete Step-by-Step Guide

Sell your surplus daytime solar units back to the national grid through a bidirectional green meter. Learn the eligibility rules, required NOCs, transformer limits, and exact costs across LESCO, IESCO, K-Electric, MEPCO, and FESCO.

⚡ Calculate Net Metering Savings → 📋 View Required Documents Checklist
All Net Metering Application Process DISCO Rules Green Meter Costs 10kW Net-Metered Systems
NEPRA Approved Workflow

The 7-Step Green Meter Installation Process

Official procedural roadmap approved by NEPRA for converting residential and commercial connections to bi-directional billing.

1

Verify 3-Phase Meter & Sanctioned Load

Net metering is granted exclusively to 3-phase electricity meters. If you currently have a single-phase connection, submit an application to your local DISCO sub-division to upgrade your sanctioned load.

2

Hire AEDB-Certified Solar Installer

Only installers certified with the Alternative Energy Development Board (AEDB) / PPIB can sign and stamp your engineering design and structural stability documents for DISCO approval.

3

Prepare Technical Documentation

Prepare Single Line Diagrams (SLD), inverter NEPRA compliance certificates (anti-islanding protection), earthing resistance test reports (< 5 Ohms), and solar panel flash test data.

4

DISCO Site Inspection & Load Flow

Engineers from your DISCO inspect the local distribution transformer capacity (NEPRA limits total solar generation to 80% of the transformer's rated capacity).

5

Sign Connection Agreement (Schedule-I)

The consumer and the DISCO sign the 3-year standard bilateral power purchase agreement detailing export credit settlement and billing reconciliation.

6

Procure & Test Green Meter

Purchase a DISCO-approved bidirectional smart meter (MicroTech or Syed Bhais) and send it to the M&T (Metering & Testing) laboratory for calibration and seal testing.

7

Commissioning & Bi-directional Billing

The DISCO team installs the calibrated green meter, removes the unidirectional meter, and issues your NEPRA Generation License. Bi-directional credits begin immediately on your next bill!

Official Verification Checklist

Required Documents Checklist

Fast-Track Processing

Complete documentation package needed for fast-track processing through your local DISCO sub-division (LESCO, IESCO, K-Electric, MEPCO, FESCO):

Regional Policies

DISCO Net Metering Fees & Turnaround Timelines (2026)

Official green meter procurement charges, M&T testing laboratory fees, and average approval duration across Pakistani distribution companies.

DISCO / Distribution UtilityGreen Meter Fee (Approx)M&T Test FeeAverage Approval TimeTransformer Cap Limit
LESCO (Lahore Electric Supply)Rs. 85,000 – 110,000Rs. 15,0004 to 6 Weeks80% of Rated kVA
IESCO (Islamabad Electric Supply)Rs. 80,000 – 105,000Rs. 12,0003 to 5 Weeks80% of Rated kVA
K-Electric (Karachi)Rs. 95,000 – 125,000Rs. 18,0006 to 8 Weeks80% of Rated kVA
MEPCO (Multan / South Punjab)Rs. 75,000 – 98,000Rs. 12,0005 to 7 Weeks80% of Rated kVA
FESCO (Faisalabad Electric)Rs. 75,000 – 95,000Rs. 10,0004 to 6 Weeks80% of Rated kVA
Engineering Guides

Published Net Metering Engineering Guides

In-depth technical articles on unit export accounting, billing deductions, and transformer limitations.